Question: The CyClon project team has started gathering the information necessary to develop a project network - predecessor activities and activity time in days. The results
The CyClon project team has started gathering the information necessary to develop a project networkpredecessor activities and
activity time in days. The results of their meeting are found in the following table: Part C Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not
willing to approve additional resources. One team member pointed out that the network contained only finishtostart relationships and
that it might be possible to reduce project duration by creating starttostart lags. After much deliberation the team concluded that the
following relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days, respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags. Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days, respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.Part C Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finishtostart relationships and that it might be possible to reduce project duration by creating starttostart lags. After much deliberation the team concluded that the following relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days, respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock