Question: 8. 15 D 10 END B 10 - E 15 H 10 20 G 15 15 All times are in seconds in the fence diagram.
8.
15 D 10 END B 10 - E 15 H 10 20 G 15 15 All times are in seconds in the fence diagram. In this precedence diagram the wal task time is 110 sec. Cycle time is 35 sec/unit The assembly line is as follows: WS1-AB WS2 - CG WS3 - ED WS4-F WS5 - H VVO WS5 - H While the line up above has 5 workstations, please calculate the theoretical minimum number of workstations? 6 N 5 3