Question: 8 . 2 0 Given the following information, complete a time - phased budget for your project. ( All cost figures are in $ 0

8.20 Given the following information, complete a time-phased budget for your project. (All cost figures are in $000 s). What are weekly planned and cumulative costs for the project?
Table for Problem 8.20 Work Package Cost per Week
\table[[Work Package,Budget,Week 1,Week 2,Week 3,Week 4,Week 5],[Staffing,9,7,2,,,],[Blueprinting,16,4,10,2,4,1],[Prototyping,17,,2,10,4,14],[Full Design,30,,,,,],[Plan,,,,,,],[Cumulative,,,,,,]]
 8.20 Given the following information, complete a time-phased budget for your