In which of the following ways is estimating effort different from estimating time?
Effort estimates include values for the length of time for project work.
Effort estimates consider the equipment needed by people to perform tasks.
Effort estimates focus more on the labor required to complete project work.
Efort estimates focus more on general activities than on specific tasks.