Question: 8 5 ) Two different approaches to load work centres in job scheduling are: A ) economic order quantity ( EOQ ) and material requirements

85) Two different approaches to load work centres in job scheduling are:
A) economic order quantity (EOQ) and material requirements planning (MRP).
B) Gantt charts and shop-floor control.
C) infinite loading and finite loading.
D) linear programming and trial-and-error.
E) linear programming and Gantt charts.