Question: 8 5 ) Two different approaches to load work centres in job scheduling are: A ) economic order quantity ( EOQ ) and material requirements
Two different approaches to load work centres in job scheduling are:
A economic order quantity EOQ and material requirements planning MRP
B Gantt charts and shopfloor control.
C infinite loading and finite loading.
D linear programming and trialanderror.
E linear programming and Gantt charts.