Question: 8 . (a) A company wishes to develop a materials requirements plan for producing a particular product (product A) over a seven week period. The
8 . (a) A company wishes to develop a materials requirements plan for producing a particular product (product A) over a seven week period. The lead time between releasing an order to the shop floor and producing a unit of product A is two weeks. The company currently has 250 units of the product in stock. The table below shows the forecast demand for product A in each of the next seven weeks. For example, the demand for product A in week 4 is 87 units. Copy the table shown below into your answer book and fill in the missing values. Your answer should clearly explain the logic behind deciding the values you have entered.
(10 marks)
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Demand | 74 | 90 | 71 | 87 | 99 | 83 | 57 |
| On-hand at end of week | |||||||
| Order |