The demand for subassembly S is 140 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 2 units of V,2 units of W, and 1 unit of x. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week to "make x,2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Suppose that in addition to 140 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 90 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).
\table[[Item,Week,\table[[Lead Time],[(weeks)]]],[1,2,3,4,5,6,7,8],[s,Gross req,,,,,,,,,2],[,On hand,,,,,,,,],[,Net req,,,,,,,,],[,Order receipt,,,,,,,,],[,Order release,,,,,,,,]]
 8: Ch 14 numeric Question 5, Problem 14.9 HW Score: 48.72%,3.9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!