Question: 8. Construct the activity-on-node diagram for the following project which comprises of the tasks A, B, C, D, E, F, G, H a) A,B, and

8. Construct the activity-on-node diagram for the
8. Construct the activity-on-node diagram for the following project which comprises of the tasks A, B, C, D, E, F, G, H a) A,B, and C, the first activities of the project can be started simultaneously. b) Astivity D can start immediately after tasks A and B are completed. c) Aativity E succeeds task C d) Activity F cannot be started until task A is completed. e) Activity E precedes tasks G and H f) Activity D precedes task G