Question: 8. NewApp Software Production (see Problem 6 above) estimates that it takes full year for each developer to produce one app. However, after a recent

8. NewApp Software Production (see Problem 6 above) estimates that it takes full year for each developer to produce one app. However, after a recent process audit, it was discovered that each developer, on average, spends only 25 hours a week directly working on the app. Assume developers work 9 hours a day, 5 days a week, 48 weeks a year. What is the process velocity? What does a ratio of greater than 1 imply?