Question: NewApp Software estimates that it takes a full year for each developer to produce one app. However, after a recent process audit, it was discovered

NewApp Software estimates that it takes a full year for each developer to produce one app. However, after a recent process audit, it was discovered that each developer, on average, spends only 25 hours a week directly working on the app. Assume developers work 9 hours a day, 5 days a week, 48 weeks a year. What is the process velocity?

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Process Velocit... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!