Question: 8 . Task time estimates and activity sequence for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows Time

8. Task time estimates and activity sequence for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows Time (in hours)(5 Points).
Activity Time in hr. Predecessor
A 6 None
B 7.2 None
C 5 A
D 6 B, C
E 4.5 B, C
F 7.7 D
G 4 E, F
Questions:
a. Draw the network.
b. Identify the Critical Path.
c. What is the expected Project Completion?
d. What are the steps to crash the project in 1 day?
e. How do you find out the probability that the Project will be on time?