Question: 8 UNIT 2 - CHALLENGE 2 . 2 : Budge: After completing the Gantt chart for a project, Ted assigned dififerent levels of responsibility to

8
UNIT 2- CHALLENGE 2.2: Budge:
After completing the Gantt chart for a project, Ted assigned dififerent levels of responsibility to members of the project team and to some of the project stakeholders. For example, he noted that while the marketing team was writing the blog, the web development team was to provide advice on the page layout.
In Ted's RACl, he defines the marketing team as being and the web development team as being the blog.
a.) responsible for, consulted about
b.) consulted about, informed about
a) accountable for; responsible for
d) informed abouts accountable for
SUBMIT MY ANSWER
 8 UNIT 2- CHALLENGE 2.2: Budge: After completing the Gantt chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!