Question: 85 A project manager is using the earned value reporting method to manage his project. The following table shows the data collected to date. The
85
A project manager is using the earned value reporting method to manage his project.
The following table shows the data collected to date. The plan is for the project to
be complete after eight weeks. The earned value report shows data collected for the
first four weeks of the project. The number shown in the table are cumulative. What
is the schedule performance index for week 3? Based on the cost performance index
at Week 4, what is the expected at complete cost (EAC)?
Table 1: Earned value reports from the project
Week Planned Value (PV) Actual Cost (AC) Earned Value (EV)
1
00 N O CT A CO N
1000
1000
1000
3000
2000
2500
5000
5000
6000
7000
9000
7000
13000
17000
19000
20000
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock