Question: A project manager is using the earned value reporting method to manage his project. The following table shows the data collected to date. The plan

A project manager is using the earned value

A project manager is using the earned value reporting method to manage his project. The following table shows the data collected to date. The plan is for the project to be complete after eight weeks. The earned value report shows data collected for the first four weeks of the project. The number shown in the table are cumulative. What is the schedule performance index for week 3 ? Based on the cost performance index at Week 4 , what is the expected at complete cost (EAC) ? Table 1: Earned value reports from the project