Question: 9) 10)In Project Management, the critical path is the path with __________ total time and determines the __________time needed for project completion. Group of answer
9)
10)In Project Management, the critical path is the path with __________ total time and determines the __________time needed for project completion.
Group of answer choices
Shortest, Maximum
Longest, Minimum
Shortest, Minimum
Longest, Maximum 11) Slack is the amount of time that an activity can be __________ without __________ the project.
Group of answer choices
delayed, delaying
delayed, being on-time
on-time, delaying
None of the remaining choices
on-time, being on-time
Imagine you have time-series data, and after essential exploration, you found that the series displays an inverted- U-shaped response over time. As a result, you built the following regression model: Yt=0+1t+2t2+ Which of the following would hold for the linear and quadratic time coefficients? 10and201>0and2010and2>0
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts