Question: 9 . 2 7 . The following table provides the information necessary to construct a project network and project crash data: begin { tabular

9.27. The following table provides the information necessary to construct a project network and project crash data:
\begin{tabular}{cccccc}
\hline & \multirow{2}{*}{\begin{tabular}{c}
Activity
\end{tabular}} & \multicolumn{2}{c}{ Activity Time (Weeks)} & \multicolumn{2}{c}{ Activity Cost (\$)}\\
\cline {3-6} Activity & Predecessor & Normal & Crash & Normal & Crash \\
\hline 1 & - & 20 & 8 & 1,000 & 1,480\\
\hline 2 & - & 24 & 20 & 1,200 & 1,400\\
\hline 3 & - & 14 & 7 & 700 & 1,190\\
\hline 4 & 1 & 10 & 6 & 500 & 820\\
\hline 5 & 3 & 11 & 5 & 550 & 730\\
\hline
\end{tabular}
a. Construct the project network.
b. Determine the maximum possible crash time for the network, and crash the network the maximum amount possible.
c. Compute the normal project cost and the cost of the crashed project.
 9.27. The following table provides the information necessary to construct a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!