Question: 9 . 2 7 . The following table provides the information necessary to construct a project network and project crash data: begin { tabular
The following table provides the information necessary to construct a project network and project crash data:
begintabularcccccc
hline & multirowbegintabularc
Activity
endtabular & multicolumnc Activity Time Weeks & multicolumnc Activity Cost $
cline Activity & Predecessor & Normal & Crash & Normal & Crash
hline & & & & &
hline & & & & &
hline & & & & &
hline & & & & &
hline & & & & &
hline
endtabular
a Construct the project network.
b Determine the maximum possible crash time for the network, and crash the network the maximum amount possible.
c Compute the normal project cost and the cost of the crashed project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
