Question: 9 - 6 . The precedence relations and crew size required to complete a project are given in Table 9 . s For example, activity

9-6. The precedence relations and crew size required to complete a project are given in Table 9.s For example, activity E, which comes after activity C, requires 10 weeks for its complelion by a crew of six people.
(a) Construct an early start Gantt chart and identify the critical path.
(b) Calculate and chart the labor profile required to complete the project for both an early start and a late start schedule.
(c) Level the required labor as much as possible with the goal of completing the project within the time period specified in part (a).
TABLE 9-4
\table[[,Activity],[,A,B,C,D,E,F],[Immediate predecessors,-,A,A,-,B,C,D,E],[Mode 1,2,3,5,3,2,1],[, Duration (days),0,9,10,6,8,4],[Resource I required (hours/activity),5,6,5,9,6,3],[, Resource II required (hours/activity),5,,,,,],[Mode 2,1,2,4,2,1,1],[Duration (days),12,12,8,6,9,4],[Resource I required (hours/activity),7,8,16,12,5,3],[Resource II required (hours/activity),7,,,,,]]
TABLE 9-5
\table[[Activity,\table[[Immediate],[predecessors]],\table[[Time],[(weeks)]],\table[[Crew],[size]]],[A,-,4,4],[B,A,2,5],[C,A,6,3],[D,B,3,7],[E,C,10,6],[F,-,2,5],[G,D,5,6],[H,F,7,2],[I,D,E,G,1,8],[J,H,10,2]]
 9-6. The precedence relations and crew size required to complete a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!