Question: Resource leveling - assignment The precedence relations and crew size required to complete a project are given. For example activity E requires 10 weeks to

Resource leveling - assignment The precedence
Resource leveling - assignment The precedence relations and crew size required to complete a project are given. For example activity E requires 10 weeks to complete with a crew of 6 people a. Construct an early start Gantt chart b. Calculate and chart the labor profile required to complete the project Activity Predecessors Time, weeks Crew size + N W - D, E, F - 00