Question: 9. According to the PMBOK guide, generally, a project's stakeholder register should not contain information about: Select one: A. The name of a certain stakeholder

9. According to the PMBOK guide, generally, a project's stakeholder register should not contain information about:

Select one:

A. The name of a certain stakeholder

B. A stakeholder's level of influence on the project

D. Stakeholders personal views and comments on the project

10. A project manager decides to use Weekly reports, video conferencing and e-mails for communication management in a project. These can be best referred to as:

Select one:

A. Project reporting systems

B. Communication mediums

D. Information retrieval systems

11. Which of the following would not be usually included in a project progress report?

Select one:

A. progress towards resolution of problems

B. degree to which the original project objectives were met

D. milestones for the next reporting period

12. For ensuring effective communication within the project team, a project manager should:

Select one:

A. Control and monitor all communication lines within the project team meticulously

C. Establish a well-organised reporting structure which includes formal meetings and monthly progress reports

D. Always promote communication among team members and ensure appropriate feedback takes place

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!