Question: 9. An information system designed to handle ordering and scheduling of dependent-demand items is used for aggregate planning. material requirements planning. master scheduling. economic order

9. An information system designed to handle ordering and scheduling of dependent-demand items is used for

aggregate planning.

material requirements planning.

master scheduling.

economic order quantities.

enterprise resource planning.

10. Which one of the following is not an input in an MRP system?

inventory records

master production schedule

all of these are inputs

bill of materials

enterprise resource plan