Question: 9. Consider the following data table (12 Points ) Annual demand Holding cost per year Order cost per order Lead time Working days per year
9. Consider the following data table (12 Points ) Annual demand Holding cost per year Order cost per order Lead time Working days per year 2,500 $ 1.50 $ 18.75 2 days 250 a) Calculate the economic order quantity (EOQ)? b) What is the reorder point?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock