Question: 9. EOQ Calculation: Bell Tower Computer Company has annual demand for their ultrabook of 10,000 computers. They want to determine EOQ for mother boards (one

9. EOQ Calculation: Bell Tower Computer Company has annual demand for their ultrabook of 10,000 computers. They want to determine EOQ for mother boards (one per computer) which have an annual holding cost of $6 per unit, and a setup/ordering cost of $75. They want to calculate total costs and the reorder point (ROP) if the purchasing lead time is 5 days. Assume 250 working days in a year. I.) What is the EOQ of the company? Please show work, thanks

a. 40

b. 200

c. 250

d. 500

e. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer