Question: 9. Given the following project data, Normal Time (weeks) Fully Crashed Time (weeks) 6 5 4 8 8 Activity A B D E F G

9. Given the following project data, Normal Time

9. Given the following project data, Normal Time (weeks) Fully Crashed Time (weeks) 6 5 4 8 8 Activity A B D E F G un Normal Cost $2400 $3200 $3500 $4000 $2200 $1700 $2000 Fully Crashed Cost $4200 $3800 $4600 $4600 $2200 $2700 $4000 3 2 8 9 2 6 7 The following diagram shows the project in fully crashed times A(6), B(5), F(6), G(7) 24 A(6), C(4), D(1), G(7) 18 A(6), E(2), D(1),G(7) 16 Can any money be saved in the diagram above without sacrificing the minimum project completion time

Step by Step Solution

There are 3 Steps involved in it