Question: 9 In this project planning tool, the team may begin Activity C when Activity B is 67% complete. This is an example of ___________ and
9 In this project planning tool, the team may begin Activity C when Activity B is 67% complete. This is an example of ___________ and tells us that: 1 point Fast tracking: Activity B is dependent on C, but the team has decided to risk beginning work on B to save time. Crashing the schedule: Activity B is dependent on C, but the team has decided to risk beginning work on B to save time. Fast tracking: Activity C is dependent on B, but the team has decided to risk beginning work on C to save time. Crashing the schedule: Activity C is dependent on B, but the team has decided to risk beginning work on C to save time