Question: 9. The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could

9. The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could take is 65 days. The most likely duration is 50 days. variance equals (P - O) / 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!