Question: 9. The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could
9. The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could take is 65 days. The most likely duration is 50 days. variance equals (P - O) / 6