Question: The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could take
The PM estimates the project schedule duration approximately resembles a beta distribution. The shortest possible duration is 25 days. The longest the project could take is 65 days. The most likely duration is 50 days. What is the variance of this project