Question: 9 . While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path. What
While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path.
What should the team member do immediately?
A Recommend the project be placed on hold for a day to avoid the risk
B Document the risk in the risk register
C Draft an emergency fallback plan since the critical path is in jeopardy
D Generate a risk report using quantitative and quantitative analysis of the identified risk to alert the team of the schedule impacts