Question: While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path. What should the
While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path. What should the team member do immediately?Select one:a. Recommend the project be placed on hold for a day to avoid the riskb. Document the risk in the risk registerc. Generate a risk report using quantitative and quantitative analysis of the identified risk to alert the team of the schedule impactsd. Draft an emergency fallback plan since the critical path is in jeopardy