Question: 9-06 (Algorithmic) Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 7 4 8

9-06 (Algorithmic) Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 7 4 8 6 7 2 10 7 Identify the critical path. A-D-G How much time will be needed to complete this project? fill in the blank 2 20 weeks. Can activity A be delayed without delaying the entire project? If so, by how many weeks? No If "No" enter "0". fill in the blank 4