Problem 9-06 (Algorithmic)
Consider the following project network and activity times (in weeks):

| Activity | A | B | C | D | E | F | G | H |
| Time | 6 | 6 | 8 | 5 | 6 | 2 | 10 | 7 |
- Identify the critical path.
- How much time will be needed to complete this project? weeks.
- Can activity B be delayed without delaying the entire project? If so, by how many weeks? If "No" enter "0". weeks.
- Can activity C be delayed without delaying the entire project? If so, by how many weeks? If "No" enter "0". weeks.
- What is the schedule for activity A? Enter 0 if your answer is zero.
Schedule for activity A Earliest Start _____ Latest Start _____ Earliest Finish _____ Latest Finish _____
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock