Question: 9.11 Construct a network activity diagram based on the following information: Activity Preceding Activities B A A D A E B F C D G

9.11 Construct a network activity diagram based9.11 Construct a network activity diagram based

9.11 Construct a network activity diagram based on the following information: Activity Preceding Activities B A A D A E B F C D G E, F H F 1 G H 1 9.12 You have a partial network for your project, and you are about to conduct a forward pass through it. Explain why the early start (ES) for activity G is 23 days, not 19 days. Remember, activity G is a merge activity. 16 E 23 7 G 4 14 F 19 5