Question: 9.20 Consider a project with the following information: Duration Predecessors n 0 D 3 5 7 A Activity A B D E F G H

9.20 Consider a project with the following
9.20 Consider a project with the following information: Duration Predecessors n 0 D 3 5 7 A Activity A B D E F G H A A B, C B 3 5 N 4 D 2 n C U I I a 5 E, F, G Activity Duration ES EF LS LF Slack A 3 m 00 B 8 13 5 5 7 o w wo 8 3 0 8 3 10 13 C D 10 3 10 13 12 3 5 4 13 17 N w w E 3 10 8 13 10 17 5 F 17 4 2 5 13 15 G H 5 12 22 17 22 17 a. Construct the project activity network using AON methodology and label each node. b. Identify the critical path and other paths through the network