Question: 9:28 PROJECT NAME: PROJECT START DATE: Based on Work Breakdown Structure Resources both Flat Rate / Hourly Based. Other than Resources being used. WBS Code

9:28 PROJECT NAME: PROJECT START DATE: Based on Work Breakdown Structure Resources both Flat Rate / Hourly Based. Other than Resources being used. WBS Code / Work Package / Activity / Labor Charges. Materials / Equipment Direct Costs Indirect Costs SI Resources Hours / U. Rate T. Rate Weeks Licenses and Permits $400 Software Programmers 35 100 3500 Renting a hosting space $800 Quality Tester 150 3000 Dell Server $4000 TOTAL ESTIMATED COSTS: $22,500. CONTINGENCIES: Assuming a percentage of 10%. Therefore, the Contingency Reserve = $22, 500 x 10% = $2, 250. TOTAL PROJECT COST BASELINE: $22, 500 + $2, 250 = $24, 750/- AA e2.alphacollege.ca A m