Question: 9.4. Construct a network from the information in the following table and identify all the paths in the network, compute the length of each, and

9.4. Construct a network from the information in

9.4. Construct a network from the information in the following table and identify all the paths in the network, compute the length of each, and indicate the critical path: Activity Activity Predecessor Time (Weeks) 1 7 2 - 10 3 1 6 4. N 5 2 5 6 4 3 3,4 7 5, 6 2