Question: Construct a network from the information in the following table, identify all the paths in the network, compute the length of each, and indicate the

Construct a network from the information in the

Construct a network from the information in the following table, identify all the paths in the network, compute the length of each, and indicate the critical path. Activity Activity Predecessor Time (weeks) 1 7 2 10 3 I 6 4 2 3 2 3.4 3 5,6 How many weeks of slack are available for activity 5? Jou 5 6 7 T6