Question: 9.A key objective when performing a technical evaluation of a contractors proposal is to ensure the labor hours, labor types, and/or material kinds and quantities
9.A key objective when performing a technical evaluation of a contractors proposal is to ensure the labor hours, labor types, and/or material kinds and quantities used as a basis to support the overall proposal costs are considered fair and reasonable.
(5 Points)
A)True
B) False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
