Question: choose the correct multiple choice A key objective when performing a technical evaluation of a contractor's proposal is to ensure the labor hours, labor types,
choose the correct multiple choice A key objective when performing a technical evaluation of a contractor's proposal is to ensure the labor hours, labor types, and/or material kinds and quantities used as a basis to support the overall proposal costs are considered fair and reasonable.
(5 Points)
1.True