Question: A 1 - year project has a total contract value of $ 5 0 , 0 0 0 , and the Planned Value ( PV

A 1-year project has a total contract value of $50,000, and the Planned Value (PV) is equally distributed over the 12 months. At the 6-month mark, it is noted the Earned Value (EV) is $20,000, and the Actual Cost (AC) is $15,000.
Based on the scenario above, the project is:
behind schedule and under cost.
on time and under cost.
on time and over cost.
ahead of schedule and under cost.
behind schedule and over cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!