Question: Given the following information for a 1 year project, use EVM calculations to answer the following questions. Each ar PV = EV = AC =

Given the following information for a 1 year project, use EVM calculations to answer the following questions. Each ar
PV=
EV=
AC=
BAC=
$24,000 PV = Planned Value
$20,000 EV = Earned Value
$30,000 AC = Actual Cost
$120,000 BAC = Budget at completion
1. What is the value of the CV?
2. What is the value of SV?
3. Estimate at completion (EAC)
4. Is the project on track as per the planned project progress?
5. How long will it take to finish the project?
Answer Format:
For dollar values do not enter $ signs and do not enter commas.
For negatives use a hyphen i.e.-1000
For no answer enter no
For yes answer enter yes
For percents enter to 2 decimals n.nn %
For month enter month i.e.10 monthl

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!