Question: a 10 none b 11 a c 5 b d 4 b e 12 a f 3 c,d g 7 f h 11 e i
| a | 10 | none |
| b | 11 | a |
| c | 5 | b |
| d | 4 | b |
| e | 12 | a |
| f | 3 | c,d |
| g | 7 | f |
| h | 11 | e |
| i | 3 | g,h |
the propsed production schedule is 8 hours and 40 units per shift. ( PLEASE ANSWER IN MINUTES)
A. Draw the precedence diagram
B. calucalte total task time
C. Calculate Takt Time.
D. calucalte the minimum number of workstations
E. develop the workstation assignment using the largest eligible task rule . how many workstations does your solution require? be sure to list which activities are assigned to a particular workstation. is the line balanced?
F calucalte idle time
G. calculate the percentage of idle time
H. calculate the efficiency.