Question: A 17-month bridge construction project includes current-year payments to the contractor of $312,000 on March 1, $600,000 on July 1, and $360,000 on November 1.
A 17 -month bridge construction project includes current-year payments to the contractor of $312,000 on March 1, $600,000 on July 1 , and $360000 on November 1 . Calculate the weighted average accumulated expenditures for the year ended December 31. Weighted average accumulated expenditures