Question: A 17-month bridge construction project includes current-year payments to the contractor of $186,000 on March 1, $522,000 on July 1, and $354,000 on November 1.

A 17-month bridge construction project includes current-year payments to the contractor of $186,000 on March 1, $522,000 on July 1, and $354,000 on November 1. Calculate the weighted average accumulated expenditures for the year ended December31. Weighted average accumulated expenditures