Question: Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 5 10 none B 3 5 9

Activity

Optimistic Time Estimate

(weeks)

Most Likely Time Estimates (weeks)

Pessimistic Time Estimates (weeks)

Immediate Predecessor(s)

A

3

5

10

none

B

3

5

9

A

C

5

7

13

A

D

4

512

B

E

5

11

16

C

F

3

4

5

D, E

G

2

7

10

D, E

H

5

511

F

I

67

G

J

3

3

3

H, I

A.)Using the information given, construct a network diagram using AON notation.

B.) Using the information given, calculate the expected time for each of the project activities.

C.) Using the information given, calculate the variance for each of the project activities.

D.) Using your results from Problems B and C, Calculate the completion time for this project.

E.) Identify the activities included on the critical path of this project.

F.) Using your results from Problem D and E, Calculate the probability that the project will be completed in 38 weeks.

G.) Calculate the probability that the project will be completed in 42 weeks.

Step by Step Solution

3.41 Rating (148 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

AUsing the information given construct a network diagram using AON notation B Using the information given calculate the expected time for each of the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

635dc41150280_178686.pdf

180 KBs PDF File

Word file Icon

635dc41150280_178686.docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!