Question: a . ( 4 Points ) Identify the critical path by forward and backward paths. For the tasks that are not on the critical path,

a.(4 Points) Identify the critical path by forward and backward paths. For the tasks that are not on the critical path, identify their slacks.
\table[[Task,Budget,\table[[Duration],[(days)]],\table[[Immediate],[Predecessors]],\table[[Shortest Time],[Possible]],\table[[Acceleration],[Cost per day]]],[A,$200,2,None,2,],[B,$500,5,A,3,$30
 a.(4 Points) Identify the critical path by forward and backward paths.