Question: Consider the following information about a small project: Task Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A 2 None 1 $70
Consider the following information about a small project:
| Task | Duration (days) | Immediate Predecessors | Shortest Time Possible | Acceleration Cost per day |
| A | 2 | None | 1 | $70 |
| B | 4 | A | 2 | $40 |
| C | 8 | A | 4 | $10 |
| D | 6 | A | 5 | $20 |
| E | 7 | B | 5 | $30 |
| F | 4 | D | 3 | $60 |
| G | 5 | C,E,F | 4 | $60 |
- Draw the network diagram.
- In above network diagram, identify the critical path by forward and backward paths. What is the duration of the project? For the tasks that are not on the critical path, what are their slacks?
- Find the cost-effective way to reduce the completion time by 3 days.
Note: When you need to accelerate multiple tasks at the same time, please identify them in a single step, such as: Step **: Accelerate task(s) _** and ** by ** days.
Step 1: Accelerate task(s) by day(s) Step 2: Accelerate task(s) by day(s) Step 3: Accelerate task(s) by day(s)