Question: A 4000 square foot ceiling joist system has been installed using 2X 6 material spaced at 16 on center. Calculate the total number of

A 4000 square foot ceiling joist system has been installed using 2"X 

A 4000 square foot ceiling joist system has been installed using 2"X 6" material spaced at 16" on center. Calculate the total number of manhours that it will take to complete the ceiling joist system installation if the production rate is 2-1/2 manhours per 100 square feet installed. I

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the total number of manhours required to complete the ceiling joist system installation ... View full answer