Question: A 5 C2 F 6 Start End D7 E 4 B 3 Key Activity Duration Using the network diagram provided above, select all the correct

A 5 C2 F 6 Start End D7 E 4 B 3 Key Activity

A 5 C2 F 6 Start End D7 E 4 B 3 Key Activity

A 5 C2 F 6 Start End D7 E 4 B 3 Key Activity Duration Using the network diagram provided above, select all the correct choices: The critical path is BDCF Activity C has 5 days of slack The shortest amount of time needed to complete this project is 18 days | The critical path is BEF | The shortest amount of time needed to complete this project is 13 days Activity C has 0 days of slack The critical path is ACF