A 75,000-ton limestone quarry cost $2,000,000 to develop. Annual gross income for the quarry in years 1 through 5 is estimated at $1,000,000. The annual production level during years 1-5 is estimated to be 10,000 tons. The percentage depletion allowance for limestone is 5%. Assume that depletion charges do not exceed 50% of taxable income. Find the estimated depletion for year 5 based on the percentage depletion method and the cost depletion method (state the depletion factor pt as part of your solution in $ per ton).