Question: ( a ) A certain project takes 4 0 days along the critical path and has a variance of 9 days. Compute the expected completion

(a) A certain project takes 40 days along the critical path and has a variance of 9 days. Compute the expected completion time for the project with the following probabilities:
(i)94.5%
(ii)46%
(iii)75%
\table[[Normal variate,Probabilities],[0.5,0.308],[0.1,0.46],[0,0.5],[1,0.841],[0.69,0.75],[1.6,0.945]]