Question: 3) Activity (A) Optimistic (3 days) most likely (4 days) pessimistic (5 days) predecessor (none) Activity (B) Optimistic (2 days) most likely (2 days) pessimistic

3)

Activity (A) Optimistic (3 days) most likely (4 days) pessimistic (5 days) predecessor (none)

Activity (B) Optimistic (2 days) most likely (2 days) pessimistic (5 days) predecessor (none)

Activity (C) Optimistic (5 days) most likely (6 days) pessimistic (10 days) predecessor (A & B)

Activity (D) Optimistic (8 days) most likely (10 days) pessimistic (12 days) predecessor (A)

Activity (E) Optimistic (2 days) most likely (4 days) pessimistic (6 days) predecessor (C)

3a) Create an AON network diagram for this project.

3b) Using PERT assumptions, calculate the individual expected times (Te) for each activity.

3c) Which tasks are on the critical path, and what is the expected completion time for the project?

3d) What is the likelihood that you can complete this project in 15 days? See the attached chart or use MS Excel.

3e) Now assume more limited resources. say that only one person is doing all these tasks and that he or she cannot do them simultaneously. Now, what is the new critical path and expected time?

3f) How much time does it save to do this project with two people instead of one person? How much more does it cost to have two people instead of one person if each person working costs $500/day? Would it be worth using the second person if it would lead to a project bonus of $5,000 bonus for early delivery? Why or why not?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!